The resource

Progress & Milestones

Area-1-Reserves-Map-2026

Offshore & Onshore Area 1

To date, approximately 65 Tcf of recoverable natural gas has been discovered in the Offshore Area 1. The results to date of the drill stem testing (DST) program in the Prosperidade and Golfinho/Atum complexes demonstrate the outstanding flow characteristics of the reservoirs.

Project milestones

2010, February First discovery, Area 1
2014, December Government passes LNG Decree Law
2015, October Reserves certified, 13 MTPA
2018, February Plan of development approved
2019, June FID $20B committed
2019, August Construction starts
2019, September TotalEnergies becomes Operator
2021, April Declaration of Force Majeure
2026, January Lifting of Force Majeure and Resumption of Construction Activities
2029 First LNG cargo